
Conservation of an unfinished construction project allows one to suspend the standard construction period, transfer the customer's rights to another person by alienating the object, etc.
The procedure for conservation of unfinished construction projects in Belarus is established in the following regulations:
Conservation is possible in relation to one of the following objects:
However, state registration of the creation of an unfinished mothballed construction project as a real estate object is carried out only in relation to an unfinished capital structure (building or structure) and when individual structural elements of the building (structure) have already been created or a separate stage of work has been completed (for example, there are buried (underground) structures, foundations have been partially or fully constructed, etc.).
Voluntary suspension of construction (temporary cessation of construction work) is allowed for a period of up to 3 months by decision of the customer
(developer) or contractor, for example, due to non-payment by the customer for work performed, identification of deficiencies in the contractor’s work that may pose a threat to the safety and reliability of the facility, and for other circumstances, the list of which is given in paragraphs. 1 and 2 tbsp. 62 of Law No. 300-Z.
Conservation of an object is allowed for a period of more than 3 months to 3 years by decision of the customer (developer) when financing the construction from its own funds, the Council of Ministers or the executive committee - when financing from budgetary funds (clauses 3 and 5 of Article 62 of Law No. 300-Z). The contractor has no right to make such a decision.
An approximate list of reasons why conservation can be carried out is established in paragraph 5 of Art. 62 of Law No. 300-Z, for example, the lack of funds from the customer or developer for further financing of construction, the impossibility of providing construction with building materials and equipment within the time period established by the contract.
The decision on conservation can be made within one month after the expiration of a three-month period of suspension of construction or without suspension of construction upon the actual cessation of construction work, when the reasons (circumstances) for conservation have already arisen.
Requirements for the form of such a decision are not established, however, in accordance with paragraph 6 of Art.
62 of Law No. 300-Z must reflect:
Within 10 working days after making a decision to mothball the facility, the customer (developer) or contractor is required to send a corresponding notification to the state construction supervision body (clause 5 of Regulation No. 343).
Within 14 calendar days from the date of the decision to mothball an unfinished construction project, the following are drawn up (Clause 7, Article 62 of Law No. 300-Z):
The forms of the conservation act, statements, as well as the list of conservation works are approved in Appendix A to TCP 45-1.03-165-2009.
The conservation act and the list of works and costs are drawn up by the customer (developer) or contractor. The conservation act must contain the estimated cost of the volumes of construction work performed up to the moment of conservation, as well as statements for unused building materials and uninstalled equipment (paragraph 2, paragraph 1, article 62 of Law No. 300-Z).
The above documents are signed by the head of the customer (developer) and the head of the contractor, and the list of conservation works is additionally signed by the head of the design organization.
Based on the list of conservation works, the developer of the project documentation draws up an estimate taking into account measures to ensure the safety of the unfinished construction project and technical documentation for its conservation.
For this purpose, the customer, on a contractual basis, transfers to the design organization the corresponding task, list of works and as-built documentation (clause 4.8 of TCP 45-1.03-165-2009).
The design organization develops this documentation within the time limits established in the decision on conservation.
Construction work for the conservation of an unfinished construction project, as provided for in the estimate, is carried out by the contractor under an additional agreement to the construction contract (clause 8 of Article 62 of Law No. 300-Z).
The additional agreement provides (clause 8 of article 62 of Law No. 300-Z):
The transfer of a mothballed unfinished construction facility is formalized by signing a bilateral acceptance certificate.
The acceptance certificate must contain the information specified in clause 78 of the Rules
No. 1450, in particular, the volume and cost of construction work actually performed by the contractor, a list of as-built documentation transferred to the customer, etc.
Upon completion of the conservation measures, the customer reimburses the costs caused by the need to terminate the construction of the facility (construction work) and conservation of the facility, and the contract is terminated (clause 49 of Rules No. 1450).
Author: Maria Azarova, junior lawyer
Maxim Lashkevich, partner, director
LLC "GRATA International BW"